          <sub id="abdgh"><ul id="abdgh"><dd id="abdgh"><form id="abdgh"><rt id="abdgh"></rt></form></dd></ul><samp id="abdgh"><section id="abdgh"><colgroup id="abdgh"><th id="abdgh"><link id="abdgh"><area id="abdgh"><dt id="abdgh"><style id="abdgh"><hgroup id="abdgh"></hgroup><hgroup id="abdgh"></hgroup><dt id="abdgh"></dt></style><strike id="abdgh"></strike><keygen id="abdgh"><th id="abdgh"><dd id="abdgh"></dd></th></keygen></dt><optgroup id="abdgh"></optgroup></area></link></th></colgroup></section></samp><var id="abdgh"><ins id="abdgh"><canvas id="abdgh"><tr id="abdgh"><optgroup id="abdgh"></optgroup></tr></canvas></ins></var><object id="abdgh"><ol id="abdgh"><dt id="abdgh"></dt><ul id="abdgh"><source id="abdgh"></source></ul></ol></object><thead id="abdgh"></thead></sub><tbody id="abdgh"></tbody>

             
              首页  >> 新闻中心  >> 境外业务动态   
             

            中色股份印度锌渣项目80米烟囱成功安装





            来源:中色股份 作者:苏保华
            发布时间:2019-04-02 打印
             

            2019年3月20日,开元棋牌集团出资企业开元棋牌金属建设股份有限公司承建的印度锌渣项目传来喜讯,脱硫车间的80米钢架烟囱安装完成。

            为高质量完成项目最高烟囱的建设安装,印度锌渣项目部技术团队严把安全关、质量关、进度关。安全方面,安排一名安全员专职守卫钢结构的拼、吊、装全过程,确保每一个环节风险可控。按照安装规范,烟囱及钢架的垂直度偏差不能超过80mm,项目工程师坚守现场指挥并核实主控数据,最终实现偏差小于40mm。为确保项目施工进度,该项目结构团队前瞻性地改变分包单位部件安装的方法,提出先地面拼装成模块、后分段吊装的方法,缩短工期近2个月。

            随着烟囱的校准完毕,整个项目也步入了工程收尾阶段。截至2019年3月,项目总体进度已完成84.1%,目前现场设备单体调试已逐步展开,项目竣工在望。

             

             

             

             

             


             